Exercise 1 The Hoisting System

A drillstring with a buoyant weight of 200,000 lbs must be pulled from the well. A total of 8 lines are strung between the crown block and the travelling block. Assuming that a four sheave, roller bearing system is being used.

a. The tension in the fast line :

200,000

F

T

8 x 0.842

Tf = 29691 lbs

b. The tension in the deadline

^ _ 200,000 An — ~

TD — 25000 lbs

c. The vertical load on the rig when pulling the string

Total = 200000 + 29691 + 25000 = 254691 lbs

Exercise 2 The Mud Pumps

Consider a triplex pump having 6in. liners and 11in. stroke operating at 120 spm and a discharge pressure of 3000 psi.

a. The volumetric output at 100% efficiency

62 x 11 x 1.0 x 120

Q =

98.03 = 485 gpm

b. The Horsepower output of the pump when operating under the conditions above.

HP = 3000 x 485

1714 = 849 hp

C O N T E N T S

1. INTRODUCTION

2. DRILLPIPE

2.1 Drillpipe Stress and Failure

2.2 Drillpipe Inspection

3. TOOL JOINTS

4. HEAVY WALL DRILLPIPE (HWDP)

5. DRILL COLLARS

5.1 Special Types of Collar

6. OTHER DRILLSTRING COMPONENTS

6.1. Stabilisers

6.2 Roller Reamer

. 6.3 Shock sub (vibration dampener)

6.4. Subs (substitutes)

6.5. Drilling Jars

7. DRILL STRING DESIGN

7.1. Design of a Stabilised String

7.2 Bending Moments in String Design

7.3 Length of Drillcollars

7.4 Drill Pipe Selection

7.4 Design Procedure

Exercise 1 The Hoisting System

Комментарии запрещены.